This spring, when North Carolina’s top utility regulator abruptly canceled bidding for new Duke Energy large solar contracts for 2026, critics filed an array of legal motions in protest, calling the unilateral order from the chair of the Utilities Commission “arbitrary and capricious” — and likely illegal.
But as the cases dragged on through the summer and fall, the clean energy industry and its advocates began to worry they had lost by default: The year was almost over, leaving no time for Duke to solicit proposals for new solar projects.
Now, the loss is official. On Monday, as part of its decision approving Duke’s long-term carbon reduction plan, the commission ruled that some solar megawatts the company had planned to procure in 2026 should be punted to future years. On Tuesday, the panel rejected pleas from a clean energy trade group and a coalition of nonprofits that it “reconsider” its spring order.
The rulings mean Duke will contract for an additional 2.3 gigawatts of solar to come online by 2034, the company says, bringing the total added under a 2021 state law to about 6.4 GW. That figure reflects over a gigawatt of solar foregone this year alone.
“ We just completely skipped a year of solar procurement in the state,” said Nick Jimenez, senior attorney with the Southern Environmental Law Center, which appealed the spring order on behalf of the Southern Alliance for Clean Energy, Vote Solar, and the Sierra Club.