Russia could turn underused natural gas infrastructure into a new source of electricity. Gazprom plans to convert idle gas compressor facilities into power plants. The proposed pilot projects could add 400 megawatts (MW) of generation capacity.
The initiative aims to address electricity shortages across southern and central Russia. It also targets growing demand from data centers, which require substantial amounts of power. Gazprom believes existing industrial sites could offer a faster and cheaper route to additional generation.
Anatoly Shapovalo, a Gazprom department head, said the company had identified projects with 400 MW of combined potential capacity. The conversions could avoid some of the expense and construction time associated with developing conventional power plants.
Gas compressor stations help maintain pressure across natural gas transmission networks. Their compressor units keep gas flowing through pipelines over long distances. However, changing export patterns have reduced the need for some of Gazprom’s infrastructure.
Russian gas supplies through the Yamal-Europe and Nord Stream pipelines stopped following the invasion of Ukraine. Gas transit through Ukraine also ended at the start of 2025.
Consequently, parts of the country’s extensive gas transmission network now operate below their previous capacity. Gazprom wants to put selected facilities to work generating electricity instead.
Shapovalo said converting existing facilities would cost less than constructing power plants from scratch. Reusing suitable infrastructure could also shorten development timelines. However, Gazprom has not identified the sites selected for its pilot projects.
The company also has not disclosed the expected investment. The 400 MW figure represents planned pilot capacity, not electricity already available to the grid.