UK developer Push Power has installed a 2.8 MW rooftop solar installation at Bentley Motors headquarters in Crewe, England, in a project covering four roofs at the manufacturers new paint shop facility.
The installation saw Push Power work with a local partner to deploy a single drone to lift 2,030 solar panels at a height of more than 20 meters. The developer estimates using drones halved the installation time while delivering a safer working environment for engineers, reduced manual handling and, by bypassing diesel-fueled telehandlers, reduced construction vehicle emissions at the site. Push Power reported that lifting panels via drone technology resulted in an installation rate of about one panel per minute, and the full installation was complete in two weeks.
Loading limits on the rooftop presented the main challenge for the installation, according to Push Power. “We couldn’t simply set full pallets down where the installers needed them,” Matt Moss, project manager at Push Power told pv magazine. “We delivered panels in small batches as the roof team needed them. That avoided having to unload and redistribute a full pallet on the roof.
“Also, of course, the weather in November and the shortness of daylight,” Moss added. “If we had the luxury of doing the work in the summer months, we could have completed in even less time.”
The developer used 515 W JA Solar panels at the site, with each module weighing approximately 30 kg. No modifications to the panels were required, according to Push Power, and each was lifted using a specially designed bag carried by an XAG P150 cargo drone.