German DSO cuts residential solar grid connection approval time to 5 minutes

pv magazine Global logo

Published on

Add as a preferred source on Google
German DSO cuts residential solar grid connection approval time to 5 minutes

Grid operators across Germany are facing a growing number of connection requests for battery energy storage systems and rooftop solar installations. To manage the increasing workload, distribution system operators (DSOs), including Netze BW, are turning to digital solutions.

The southern German grid operator has unveiled an automated assessment process for PV systems with capacities of up to 15 kW. The system can reduce processing times from an average of 12 days to around five minutes in areas where sufficient grid capacity is available.

Netze BW launched the system in late July 2026, following a testing and rollout phase that began in November 2025. Since then, the company has received more than 16,000 grid connection requests for small-scale PV installations, according to Angelika Ruß, a Netze BW representative, speaking at a press briefing.

More than 5,000 applicants have already received automated responses within five minutes. Marc Schmidt, also of Netze BW, said these responses constitute binding grid connection approvals and specify the connection point for installations up to 15 kW.

Jörg Reichert, chairman of Netze BW’s management board, highlighted the company’s strong performance in a digitalization index published this summer by Germany’s Federal Network Agency (Bundesnetzagentur), the country’s energy regulator.

“The energy transition cannot be achieved with a single mouse click – but the right digital solutions can certainly speed things up significantly,” said Reichert. “Anyone wanting to connect a photovoltaic system should be able to reach their goal without paperwork, waiting on hold, or follow-up inquiries.”

In a recently published comparison of German DSOs, Netze BW recorded an average processing time of 12 days for manually assessed grid connection requests, compared with a median of 80 days across all operators.


Source link

Disclaimer

We strive to uphold the highest ethical standards in all of our reporting and coverage. We TheMorningPulse.fyi want to be transparent with our readers about any potential conflicts of interest that may arise in our work. It's possible that some of the investors we feature may have connections to other businesses, including competitors or companies we write about. However, we want to assure our readers that this will not have any impact on the integrity or impartiality of our reporting. We are committed to delivering accurate, unbiased news and information to our audience, and we will continue to uphold our ethics and principles in all of our work. Thank you for your trust and support.