Delivery partners for the United Kingdom’s East Coast Cluster (ECC) have awarded more than £2.25 billion ($2.95 billion) in supply chain contracts to domestic companies as construction progresses across Teesside, marking a major industrial milestone during a November 23, 2026, site visit to Teesworks by Minister for Local Energy and Jobs Martin McCluskey MP and Redcar MP Anna Turley.
Comprising the Northern Endurance Partnership (NEP), which is constructing Teesside’s onshore and offshore CO2 transport and storage network, and Net Zero Teesside Power (NZT Power), the world’s first commercial-scale gas-fired power station equipped with carbon capture and storage (CCS), the cluster has placed over 350 contracts and is on track to create and sustain more than 3,000 jobs.
More than half of the projects’ total supply chain content has been fulfilled by UK businesses across engineering, manufacturing, construction, and technical services.
NEP Managing Director Rich Denny confirmed that the partnership’s CO2 transport and storage network has surpassed 45% delivery, unlocking substantial contract packages for regional manufacturers and service providers.
In Hartlepool, Corinth Pipeworks UK, working alongside Marubeni-Itochu Tubulars Europe Plc and Eisenbau Kramer GmbH, contributed to supplying 105 kilometers of onshore and offshore linepipe while expanding local apprenticeship roles.
Meanwhile, Teesside-headquartered operations and maintenance (O&M) specialist pX Group secured a landmark contract from NEP and NZT Power to recruit roughly 100 local personnel and five apprentices to manage both facilities from commissioning through commercial operations.
Relevant: UK Opens New Route For CCUS Projects To Join East Coast Cluster Teesside
Similarly, Thirsk-based Potter Plant Hire has created 74 jobs, including 70 plant operators recruited within an average 13-mile radius of Teesworks, since joining main contractor Balfour Beatty on the NZT Power build in June 2025.
Source link