Russia has delivered the first fuel for the eighth and final reactor at China’s Tianwan nuclear power plant, bringing the site a step closer to becoming the world’s largest by installed nuclear capacity. The plant, on the Yellow Sea coast in Jiangsu province, is expected to reach about 9.1 gigawatts once all eight units are operating.
Rosatom’s nuclear fuel division, managed by TVEL, supplied the initial core load and a reserve batch of fuel assemblies for Unit 8’s VVER-1200 reactor. China National Nuclear Power said the unit also completed hot tests on Wednesday, marking a separate milestone in preparations for startup.
The hot tests subjected reactor systems to the temperatures and pressures they are designed to encounter during normal operation. The checks covered equipment on both the nuclear and conventional sides of the plant to verify that it met design requirements. They followed earlier cold tests that checked the primary circuit and its components for leaks.
The Novosibirsk Chemical Concentrates Plant in Russia manufactured the fuel. The delivery was made under a contract that TVEL signed in July 2019 with two companies under China National Nuclear Corporation to supply fuel for Tianwan’s Units 7 and 8.
Unit 7 is being prepared for commercial operation, while Unit 8 remains in commissioning. The two units were scheduled to enter commercial service in 2026 and 2027, respectively.
Tianwan’s expansion adds two Russian-designed Generation III+ VVER-1200 reactors to a site that already has six units. The first four use Russian-designed VVER-1000 reactors and entered commercial operation between 2007 and 2018.