Following a record 5 GW of large-scale renewable energy investment to the end of Q3 2026, up from 4.9 GW in 2025, the Clean Energy Regulator (CER) has raised the lower bound of its 2026-2027 final investment decision (FID) projection from 6 GW-8 GW, to 8 GW-16 GW.
“In the Q4 2025 Quarterly Carbon Market Report (QCMR), we projected that between 6 and 16 GW of large-scale renewable generation capacity would reach FID over 2026 and 2027. The record level of investment activity observed during 2026 has significantly reduced downside risks to this outlook,” the Q3 2026 QCMR report says.
Of the nine projects to reach FID in Q3 2026 totalling 2.1 GW, five received support under the Capacity Investment Scheme (CIS) including two solar projects in Queensland, the 150 MW Ganymirra Solar Power Station and 150 MW Majors Creek Solar Farm.
It was the fourth-strongest quarter for solar with 1 GW of capacity reaching FID. By mid-November 2026 all investments moved year-to-date FID to 5.5 GW.
“Solar accounted for 3.5 GW of FID in 2026 to date,” the report says. “Australian Renewable Energy Agency’s (ARENA) update to their Ultra Low-cost Solar white paper identified a range of opportunities to reduce the cost of deploying utility-scale solar in Australia, which could continue to strengthen the investment case for both standalone solar and hybrid solar-and-storage projects.”
The report also says the ARENA paper highlights improved cell and module efficiency, innovation in construction and deployment models, including automation, prefabrication, modular delivery, and digital and data-driven operational and maintenance optimisation as potential pathways to lower project costs.